|
|
|||||
| Slab & Framing
Robert rented a bobcat and pneumatic jack hammer to break up and move the driveway and front sidewalk pieces into the "pit". We had one laborer to do the jack hammering while we loaded the bobcat bucket and dumped the pieces in the pit. This took all day Saturday and all afternoon on Sunday. It had rained heavily on Sunday morning so everything was a muddy mess by the end of the day. Robert then spent another evening moving several chunks of concrete to level the pile out. |
|||||
|
This compacter also vibrates to help settle the clay and compact it. We had dump trucks dump the clay which Robert then moved around with a Bobcat and compacted. It took 7 truck loads to get it to the right level. |
|||||
|
After the clay was level and to the right height we had one load of gravel dumped. Robert then graded the driveway with the Bobcat and got the surrounding area to lie right. Over the next two months we did several odd jobs to get ready for the pour. Robert compacted the gravel and we put out a layer of plastic over the entire area. We then slowly but surely laid a grid of #4 rebar on chairs and tied the junctions with wire. We got three small loads of fill dirt which we dumped around the perimeter of the stem walls to create a slope away from the building. And, we also managed to pour a new 12 ft square front porch on the house. |
|||||
|
We placed foam insulation strips along the edges (against the stem walls) for expansion if the slab wants to move. A final check with the transit to ensure that the rebar was at the right height and we were ready for the slab to be poured. |
|||||
|
Robert got a professional crew out to pour the slab. It took 2 full loads plus 2 more yards in a third truck. Unfortunately the 3rd truck driver didn't have 2 yards but only brought a bit over 1 yard, so we had to get a 4th truck out to bring the last bit to complete the pour. The first truck (shown above) had a conveyor belt to get the concrete to the back of the building. The second load needed just the regular shoot. |
|||||
|
Within an hour of the last pour they started to smooth the surface out.
It took another 3 hours before it was all nice and smooth and they could
come in with the wet cut saw to cut the crack control lines. |
|||||
|
Robert had spent all of the previous day installing the pressure
treated sills on the stem walls, inserting a thin layer of foam between
the concrete and the lumber. As we were not able to get all the
anchor bolts in place when the walls were poured Robert had to drill holes
and insert bolts where there were some missing. |
|||||
|
Robert and I were able to put up the last few small panels ourselves (after our helper left) as they were not very heavy. The new air nail gun we bought made easy work of toe nailing the sections in place. |
|||||
|
It took some work getting the two LVL's up there but Robert, a Neighbor and I managed to get them in place over the garage door span. Robert and I then made a 16" cripple wall which we placed on top of the beams. We also added some more sheets of pressboard to the corners and top plates to all the walls to make sure things don't move. In the picture above you can see the platform on wheels that Robert made to do all the high work. We got 7 of the 31 floor joists up this morning. It's not an easy job for two people. We have to get one end of the joist up on the platform, then go over to the other side and, using two ladders, heft the other end up onto the top plate. |
|||||
|
Over the weekend we put the staircase in. We used 7" risers with 11" treads. Now we are working on getting all the subfloor sheets up to the 2nd level and fastening them in place with Liquid Nails and screws. |
|||||
Copyright Reserved - Created May 2006 - Greentree Creations - e-mail Jane |